NOTICE IS HEREBY GIVEN that Galway City Council has made an order closing: -
High Street: From the Junction of Cross Street to the Junction of Shop Street.
Quay Street: From the Junction of Cross Street to the intersection with the exit from Leonardo Hotel is also to be closed to HGV traffic.
Period of Closure: 24/7 Monday 6th January 2025 to Friday 28th February 2025.
Reason: Street rehabilitation and drainage upgrade works.
Diversion Routes: Temporary diversion route will be in place via Mainguard Street, Cross Street, Flood Street, turning left on to the R336 New Dock Street to Merchants Road. Lower and further right on the R336 continuing along the Spanish Parade.
Localised access will be maintained as permitted within the limitations of those within the existing pedestrianised zone.
Document Map Road Closure Diversion Route High Street (003) (002).pdf (PDF, 972.58KB)
Advance diversion signage will be in place prior to work commencing.